Pilgangoora Lithium Project

Location: Pilbara, Western Australia

Project Type: Mining Process Plant and Equipment

RCR Resources / Pilbara Minerals

Austruct’s scope works includes shop detailing, material procurement, fabricate, surface treatment, modularisation and delivery steelworks to Port Hedland. There are approximately 1500t structural steel, 360t plateworks, 9km pipe spool fabrication, 4000sqm Rubber lining and 8km cable trays. 

*Imported material take two months longer than local Chinese GB material in procurement time. Plus due to logistic issues, the imported material were arrived 3 weeks later than original planned. Austruct’s procurement team work closely with the material supplier and project operation team to ensure the ground works can be adjusted to ensure minimum time is wasted in waiting. 

*Works were conducted while the engineering design underway. This caused significant reworks for shop detailing and fabrication works, thus impacted overall schedule. The project was finally completed on time which was in line with client’s expectations. This project can not be succeed without tireless works by Austruct team and ground workforce.